Practice: Create A Job Dependency
Objective
Create a REQUIRES Dependency.
Instructions
- In Solution Manager, select Studio.
- In the Schedule list, select Practice Schedule 1.
- Click the View button.
- Click Frequency Job 1.
- In the Job menu, click Add Dependency.
- In the Schedule Schedule frame, check that Practice Schedule 1 is selected.
- In the Job drop down list, select Windows Job 1.
- In the Dependency frame, select Requires and Finished OK.
- Click Save.