Skip to main content

On Interval -- Annual Plan -- Odd Even

Frequency Definition Wizard - On Interval, Annual Plan, Odd & Even Weeks

On Intervals

  • Essentially the On Day option, but blocked in multiples of 5 (instead of creating 6 different Frequencies)

-OR-

  • Every X number of days starting on X date
  • Start Date can be the same every year, or could be one time start date and increments keep going forever
  • Other Fields:
    • A/O/B/N flag is applicable
    • The Calendar selected will block off days listed within a Calendar AFTER A/O/B/N days are set

Annual Plan Calendars

  • Two Steps in Using Annual Plan Calendar:
    • Create/Maintain Calendar
    • Apply a Calendar to a frequency
  • A/O/B/N is NOT configurable
  • Offsets use workdays

Odd and Even Weeks

Odd Weeks

  • Every other week not necessarily Odd weeks
    • Weeks start on Sundays
  • Better defined as the opposite of Even Weeks Frequency
  • Best Practice: Use On Interval Frequency with a 14 day offset
  • Other Fields:
    • A/O/B/N flag is applicable
    • The Calendar selected will block off days listed within a Calendar AFTER A/O/B/N days are set

Even Weeks

  • Every other week not necessarily Even weeks
    • Weeks start on Sundays
    • 0 is even
  • Better defined as the opposite of Odd Weeks Frequency
  • Best Practice: Use On Interval Frequency with a 14 day offset
  • Other Fields:
    • A/O/B/N flag is applicable
    • The Calendar selected will block off days listed within a Calendar AFTER A/O/B/N days are set

Enterprise Manager

Details

Frequency Definition Wizard - On Interval, Odd & Even Weeks, Annual Plan

On Intervals

  • Essentially the On Day option, but blocked in multiples of 5 (instead of creating 6 different Frequencies)

Or

  • Every X number of days starting on X date
  • Start Date can be the same every year, or could be one time start date and increments keep going forever
  • Other Fields:
    • A/O/B/N flag is applicable
    • The Calendar selected will block off days listed within a Calendar AFTER A/O/B/N days are set

Odd and Even Weeks

Odd Weeks

  • Every other week not necessarily Odd weeks
    • Weeks start on Sundays
  • Better defined as the opposite of Even Weeks Frequency
  • Best Practice: Use On Interval Frequency with a 14 day offset
  • Other Fields:
    • A/O/B/N flag is applicable
    • The Calendar selected will block off days listed within a Calendar AFTER A/O/B/N days are set

Even Weeks

  • Every other week not necessarily Even weeks
    • Weeks start on Sundays
    • 0 is even
  • Better defined as the opposite of Odd Weeks Frequency
  • Best Practice: Use On Interval Frequency with a 14 day offset
  • Other Fields:
    • A/O/B/N flag is applicable
    • The Calendar selected will block off days listed within a Calendar AFTER A/O/B/N days are set

Annual Plan Calendars

  • Two Steps in Using Annual Plan Calendar:
    • Create/Maintain Calendar
    • Apply a Calendar to a frequency
  • A/O/B/N is NOT configurable
  • Offsets use workdays