To set a dependency:

  1. Double-click on Job Master under the Administration topic. The Job Master screen displays.
  2. Select the schedule in the Schedule drop-down list.
  3. Select the job in the Job drop-down list.
  4. Click on the Dependencies tab in the Job Properties frame.
  5. Click on the Job Dependency tab.
  6. Select the Job Related checkbox.
  7. Click the Add button. The Add Dependency dialog displays.
  8. Select the schedule for the Predecessor Job in the Schedule drop-down list.
  9. Select the job for the Predecessor Job in the Job drop-down list.
  10. Select the instance name for the Predecessor Job in the Instance Name drop-down list.
  11. Select the preferred dependency type radio button.
  12. Select the preferred option(s).
  13. Select the frequency for the Successor Job in the Frequency drop-down list.
  14. Select the instance name for the Successor Job in the Instance Name drop-down list.
  15. Click the OK button to save the changes or the Cancel button to discard the changes.
  16. Click Close ☒ (to the right of the Job Master tab) to close the Job Master screen.

To set a dependency:

  1. Double-click on Job Master under the Administration topic. The Job Master screen displays.
  2. Select the schedule in the Schedule drop-down list.
  3. Select the job in the Job drop-down list.
  4. Click on the Dependencies tab in the Job Properties frame.
  5. Click on the Job Dependency tab.
  6. Select the Frequency Related checkbox.
  7. Select the frequency in the Frequency List.
  8. Click the Add button. The Add Dependency dialog displays.
  9. Select the schedule for the Predecessor Job in the Schedule drop-down list.
  10. Select the job for the Predecessor Job in the Job drop-down list.
  11. Select the instance name for the Predecessor Job in the Instance Name drop-down list.
  12. Select the preferred dependency type radio button.
  13. Select the preferred option(s).
  14. Select the frequency for the Successor Job in the Frequency drop-down list.
  15. Select the instance name for the Successor Job in the Instance Name drop-down list.
  16. Click the OK button to save the changes or the Cancel button to discard the changes.
  17. Click Close ☒ (to the right of the Job Master tab) to close the Job Master screen.