Skip to main content
Version: OpCon 22.0 (On-Prem)

Adding Resources to Layouts

note

If you do not have the privileges to "Modify Jobs in Job Master" in at least one department, or "All Administration Functions" or "All Functions," the Select Threshold tool is disabled.

To add a resource:

Double-click on Workflow Designer under the Administration topic.

Select a schedule in the Select Schedule drop-down list.

Click, drag, and drop the Resource icon in the Tools frame to the schedule diagram.

Select the resource.

Click the OK button.

Add a Resource Dependency

Establish the dependency link by following either of the two procedures:

a. Clicking Add Dependency in the Tools frame. b. Clicking on the resource that is the object of the dependency. c. Clicking on the job in which to create the dependency. d. Proceeding to Step 7.

OR

a. Clicking Select. b. Pressing the Ctrl key then clicking on the resource that is the object of the dependency. c. Dragging the line for the link across to the job in which to create the dependency. d. Proceeding to Step 7.

Select the Resource option information (e.g., Value, Frequency) in the Resource Dependency dialog.

Click the OK button to save the added resource.

Edit a Resource Dependency

Right-click the resource dependency link (line) whose details need to be changed.

note

When clicking on the Resource Dependency link line, the line should thicken and become bold.

Click Edit. The Editing Job Dependency dialog displays.

Change the Resource Dependency option information (e.g., Value, Frequency).

Click the OK button to save the resource dependency change(s).

note

Refer to the Delete a Dependency procedure to delete resource dependencies.