Skip to main content
Version: OpCon 23.0 (On-Prem)

Setting Preferences for Gantt

note

Close and re-open the charts to refer to the change in this section take effect.

To set the preferences:

  1. Launch the Enterprise Manager application.
  2. Use menu path: EnterpriseManager > Preferences. The Preferences dialog displays.
  3. Click on the arrow (Expand Arrow     ) next to Enterprise Manager in the Preferences tree to expand the drop-down list.
  4. Click on Gantt. The Gantt settings display to the right.
  5. (Optional) Select the Show job names checkbox to display the Job names on the chart. (It is selected by default.)
  6. (Optional) Select the Show progression checkbox to refer to the percent complete for each job (based on estimated run time) on the chart. (It is selected by default.)
  7. (Optional) Select the Show dependencies checkbox to refer to the job dependency lines on the chart. (It is selected by default.)
  8. (Optional) Select the Refresh while moving events (slower) checkbox to cause dependent job boxes to move while moving a target job in the Plan Mode. (It is not selected by default.) If this option is not selected, the dependent job boxes move when the target job is dropped into a new position.
  9. (Optional) Click inside the Space between jobs(pixels) text box and type a different value to adjust the spacing between the Jobs listed in the chart (default is set to 5 pixels). The maximum setting is 10 pixels.
  10. (Optional) Select from the Themes drop-down list a different Theme for the date/time bar at the top of the Gantt chart (default is set to Windows Blue).
  11. (Optional) select from the Type of dependencies drop-down list the way job dependency lines are displayed in the Gantt chart.
  12. Click Apply to save the changes in this dialog.
  13. Click OK to save the changes and close the Preferences dialog.