Applying Master Calendars to Schedules
Theme: Configure
Who Is It For? System Administrator, Automation Engineer
What Is It?
Use this procedure to apply Master Calendars to Schedules in the Enterprise Manager.
To apply a master calendar to a schedule, complete the following steps:
- Select on Schedule Master under the Administration topic
- Select the schedule in the Schedule list
- Select the Use Master Holiday option
- Select
Save on the Schedule Master toolbar
- Select the x to the right of the Schedule Master tab to close
Configuration Options
| Setting | What It Does | Default | Notes |
|---|
FAQs
Q: How many steps does the Applying Master Calendars to Schedules procedure involve?
The Applying Master Calendars to Schedules procedure involves 5 steps. Complete all steps in order and save your changes.
Glossary
Calendar: A named collection of dates in OpCon used by schedules and frequencies to determine when automation runs or is excluded. Calendars can represent holidays, working days, or any custom date set.
Resource: A numeric variable in OpCon representing a finite pool. Jobs can be configured to require a set number of resource units to run, limiting concurrent executions and preventing resource contention.
Schedule: A named container for jobs in OpCon, built for a specific date to create that day's automation. Schedules define build settings, frequencies, and the jobs that run within them.