Annual Plan Events
Annual Plan Calendar - Event Updates
- Two Steps in Using Annual Plan Calendar:
- Create/Maintain a Calendar
- Apply the Calendar to frequency
- A/O/B/N is not configurable
- Offsets use workdays
Calendar Events
- Dates can be added or removed from a Calendar through Events
$CALENDAR:ADD,Company Holiday Calendar,05/25/2025; 05/25/2026; 05/25/2027; 05/25/2028; 05/25/2029
$CALENDAR:DEL,Company Holiday Calendar,05/25/2025; 05/25/2026; 05/25/2027; 05/25/2028; 05/25/2029
- Scenarios:
- A Job needs to run 10 working days after the 15th of month
- A Null Job scheduled to run on the 15th could submit:
$CALENDAR:ADD,Company Holiday Calendar,[[$SCHEDULE DATE(+10wd)]]
- A Job needs to run the working day before a different Job scheduled for the 15th-B
- Date calculation tool – Chronoman