Adding Schedules
To add a Schedule in Enterprise Manager, complete the following steps:
-
Select Schedule Master under the Administration topic. The Schedule Master screen displays.
-
Select
Add on the Schedule Master toolbar.
-
Enter a schedule name (up to 40 characters) in the Name field.
-
(Optional) Enter notes about the Schedule in the Documentation field. The field accepts up to 4,000 characters.
-
Select the Schedule tab.
-
(Optional) Enter a start time in the Start Time field in the Schedule Details section. If left blank, the Schedule starts at
00:00(midnight). -
Select the days of the week the Schedule runs under Workdays per Week.
-
(Optional) Select any of the following options as needed:
Option Description Multi-Instance Allows the Schedule to run as more than one instance on the same date. SubSchedule Designates the Schedule as a container Schedule called by a Container job. Conflict with Other Days Prevents the Schedule from running if it conflicts with Schedules on other days. Use Master Holiday Applies the Master Holiday calendar to the Schedule. Selected by default. -
(Optional) Select an additional holiday calendar from the Additional Holidays list.
-
Select
Save on the Schedule Master toolbar, then select OK to confirm.
Result: The Schedule is saved and appears in the Schedule Master list.
To close the editor, select Close (to the right of the Schedule Master tab).