Editing Daily Schedules
Editing a Daily Schedule modifies schedule or job information for a single date's instance in the Daily tables. Changes do not propagate to Job Master records or to any other date in the Daily tables. For example, changing a job's start time from 19:00 to 20:00 on a specific date leaves all other instances at 19:00.
You can modify the following schedule-level information:
- Schedule Start Time
- Schedule Completion Events
- Available properties for the schedule instance
You can modify the following job-level information:
- General and platform-specific job details
- All Job Automation components for the job instance
- Available properties for the job instance
You can also delete jobs from Daily Schedules.
Deleting a Container job whose subschedule(s) have never started also deletes all of that Container job's subschedules, including any spawned subschedules.
Required privileges
To modify jobs in a Daily Schedule, your role must include one of the following department-level function privileges:
- Modify Jobs in Daily Schedules (together with View Jobs in Daily Schedules)
- All Daily Schedule Functions
To modify schedule-level properties, your role must include the Modify Schedule privilege for the target schedule.
To delete jobs from a Daily Schedule, your role must include the Delete Jobs from Daily Schedules privilege.
Edit schedule information
To edit schedule information in the Daily tables, complete the following steps:
- In Solution Manager, go to Operations.
- Select Processes.
- Locate and select the schedule for the date you want to modify.
- In the right panel, select the edit icon to open the Daily Schedule Definition page.
- Modify the Start Time, Completion Events, or Instance Properties fields as needed.
- Select Save.
Result: The changes apply to the selected date's schedule instance only. The Job Master record and all other dates are unchanged.
Edit job information
To edit job information in a Daily Schedule, complete the following steps:
- In Solution Manager, go to Operations.
- Select Processes.
- Locate the job you want to edit.
- In the right panel, select the edit icon to open the Daily Job Definition page.
- Modify the applicable fields across the Task Details, Frequency, Properties, or Documentation panels.
- Select Save.
Result: The changes apply to the selected job instance only. The Job Master record and all other dates are unchanged.
Delete a job from a Daily Schedule
To delete a job from a Daily Schedule, complete the following steps:
- In Solution Manager, go to Operations.
- Select Processes.
- Select the job you want to delete.
- In the right panel, select Delete Selected Job(s).
- Confirm the deletion when prompted.
Result: The job is removed from the Daily Schedule for the selected date. If the deleted job is a Container job and its subschedule(s) have never started, all associated subschedules — including any spawned subschedules — are also deleted.