Skip to main content
Version: OpCon (Cloud - Current)

Adding Master Schedules

Theme: Configure
Who Is It For? System Administrator, Automation Engineer

What Is It?​

Use this procedure to add Master Schedules in Solution Manager.

Administration​

Required Privileges​

Adding a Schedule​

To add a Master Schedule, go to Studio and select Add. The Create Master Schedule page displays:

Master Schedule Details

Adding Schedule Name and Documentation​

To add a schedule name and documentation, complete the following steps:

  1. Enter a Schedule Name. For more information, refer to Schedules in the Concepts online help.
  2. (Optional) Enter the Documentation details. For more information, refer to Schedule Details in the Concepts online help.

Adding Schedule Settings​

To add schedule settings, complete the following steps:

  1. (Optional) Select the Multi Instance option.
  2. (Optional) Select the Sub Schedule option. Note: Selecting this option resets and disables all autobuild settings (auto build and auto delete).
  3. (Optional) Select the Conflicts with other days option.

Adding Schedule Start Time and Work Days​

To add schedule start time and work days, complete the following steps:

  1. Enter the Start Offset Hour.
  2. Enter the Start Offset Minutes.
  3. Select the Workdays.

Holiday Calendar Settings​

To configure holiday calendar settings, complete the following steps:

  1. (Optional) Select Additional Holidays.
  2. (Optional) Select the Use Master Holiday option.

Schedule Build and Maintenance​

For more information, refer to Schedule Maintenance in the Concepts online help.

note

All autobuild settings reset and become disabled when the Sub Schedule option is selected.

To configure schedule build settings, complete the following steps:

  1. (Optional) Select the Auto Build option. For more information, refer to Build Settings in the Concepts online help.
  2. Enter the number of Days in Advance.
  3. Enter the number of Days to build for.
  4. Enter the Build Offset Hours.
  5. Enter the Build Offset Minute.
  6. (Optional) Select the Overwrite option.
  7. (Optional) Select the Build on Hold option.
  8. Select Save to create the schedule or Cancel to cancel the operation.

FAQs​

Q: How do you save a new master schedule record?

After completing the required fields, select the Save button on the toolbar to save the master schedule record.

Q: What happens to autobuild settings when Sub Schedule is selected?

All autobuild settings reset and become disabled when the Sub Schedule option is selected.

Glossary​

Calendar: A named collection of dates in OpCon used by schedules and frequencies to determine when automation runs or is excluded. Calendars can represent holidays, working days, or any custom date set.

Resource: A numeric variable in OpCon representing a finite pool. Jobs can be configured to require a set number of resource units to run, limiting concurrent executions and preventing resource contention.

Privilege: A specific permission granted through an OpCon role that controls access to a feature, function, or object type. Privileges are organized into categories such as Function Privileges, Machine Privileges, Schedule Privileges, and Access Codes.

Schedule: A named container for jobs in OpCon, built for a specific date to create that day's automation. Schedules define build settings, frequencies, and the jobs that run within them.